| Writing a Scope Statement - Page 2 |
|
|
Page 2 of 2
Scope VerificationIn previous articles we discussed writing a scope statement and developing a Work Breakdown Structure in scope definition. Scope verification includes activities such as measuring, examining and testing the project deliverables to make sure they conform to the requirements in terms of specifications and quantities. Formal acceptance of the deliverable by the buyer is the objective. Scope verification is time consuming and expensive. So it is preferable to do it only the one time for each project deliverable. It is not necessary to wait until the end of the project before scope verification activities begin. Scope verification can proceed as soon as a deliverable is complete and can be measured, examined and tested. Scope verification also takes place if a contract is terminated before completion. In this case the extent of the completed works must be agreed, documented and signed off. This is particularly important if there is possibility of dispute. Scope Verification: Inputs and Outputs
Scope Change ControlWe now focus on managing and controlling the inevitable changes in project scope. The need for scope change can come from
Small changes can be approved by the Customers representative. However big changes must be approved by a "Change Control Board" comprising members from all interested parties. Big or small, the management of scope change is best accomplished with a formal documented change control system. A change control system will include the following:
The Scope Management Plan, usually a section within the Project Plan, describes how scope changes are evaluated, processed and integrated into the project. A change control procedure will be successful if the following steps are taken.
The following flow chart describes a typical change control process.
A potential change in the project scope is identified. This potential change is reviewed. If it is not considered beneficial to the success of the project but will impact the project result if left unattended, an issue is recorded in the Issues Register. The change is then evaluated. If there is no impact on the project deliverables, budget or the schedule, the change is made and documented. The Change Order Form is reviewed by the customer and / or the Change Control Board. If the change is approved it is implemented and then documented. If the change is not approved, there must be something that needs to be resolved, so an Issue is raised and resolved through that process. A sample of a Change Order Register and Change Order form can be downloaded from the templates area. They may need to be adapted to suit individual requirements. Many project managers adopt an informal approach to handling requests for changes. Unfortunately, misunderstandings often arise, things are forgotten and the project manager is forced to deliver the changed scope without any change to budget or schedule. Don't let that happen to you!
2001 © Jeb Riordan About the Author Jeb Riordan PMP, is a working project manager, currently on assignment in Thailand and enjoying every minute... Comments (0)
![]() Write comment
|



